Building
Graphics and Estimated Cost Budgets of Each Block |
Project Phase One will be started in June 2006.
The pages contains graphics and estimated cost budget of
each blocks. Building design and cost budgets are prepared
by two experts in engineering in Nepal.
|
|
|
There
are two identical classroom blocks standing in a line and
has a stair in between. In total, there are 20 classrooms;
ten for junior students and ten for senior students. Each
classroom has space for at least 15 students.
The sizes of the classrooms are 25ft
x 30ft with a clear head 8ft. The corridors of the classrooms
are facing south where we have a smoothly flowing river
and beautiful view of the surrounding mountains. |
Estimated
Cost Budget of Junior School Block: |
Names of Particular |
Nepalise Rupees
(NRS) { NRS 70 = $ 1 U.S.) |
U.S Dollar ($) { $1 = NRS
70) |
|
547,235.00 |
7,817.64 |
|
1,464,761.00 |
20,925.16 |
|
1,096,653.00 |
15,666.47 |
Total: |
3,108,649.00 |
44,409.27 |
|
155,432.45 |
2,220.46 |
|
155,432.45 |
2,220.46 |
Sub
Total: |
3,419,513.90 |
48,850.20 |
|
170,975.70 |
24,425.51 |
Grand
Total: |
3,590,489.60 |
51,292.71 |
Grant
Toal In words: |
Thirty Five Lakhas
Ninety Thousands Four Hundred Eight Nine & Sixty Paisa
Only |
Fifty One Thousands
Two Hundred Ninety Two and Seventy One Cent only. |
|
|
Boys' and
girl's hostals are two identical hostals. Boys' hostal on
the left and girls' hostal on the left of the Kitchen and
Dinning Hall. Both hostals have proper natural lighting
and each block can accommodate up to fifty students. All
the rooms have at least one window with great view of the
surrounding environment.
Older students will have a room for
three students. The ground floo of the hostal has ten rooms
for them. Younger students who need to be cared by a foster
parent, have bigger rooms on the first floor. These rooms
can be shared up to 15 students. A room is designed for
a foster parents/warden and the size of the room is same
as other staff rooms. |
Estimated Cost Budget of the
Boys' Hostals
|
|
|
|
Name of Particular |
Nepalise Rupees (NRS) { NRS 70 = $ 1 U.S.) |
U.S Dollar ($) { $1 = NRS 70) |
|
250,262.00 |
3,575.17 |
|
647,985.00 |
9,256.93 |
|
413,083.00 |
5,901.19 |
Total |
1,311,330.00 |
18,733.29 |
5% Electric Cost |
65,566.50 |
936.66 |
5% Sanitary Cost |
65,566.50 |
936.66 |
Subtotal |
1,442,463.00 |
20606.61 |
5% Contingency |
72,123.15 |
1,030.33 |
Grant Total |
1,514,586.15 |
21,636.95 |
Grant Total in
Words |
Fifteen Lakhas Fourteen Thousands Five Hundred Eight Six
and Fifteen Paisa Only. |
Twenty One Thousand Six Hundred Thirty Six and 95 cent only. |
The
Common Kitchen and Dinning Hall |
|
The common Dinning Hall and the Kitchen
are both one-storied buildings with sloped roofing and have
proper natural lighting. The hall has space for up to one
hundred students and 20 staff members although staff residents
are designed to have attached kitchens. The kitchen is for
using fire wood because gays doesn't exist in the area.
The size of the dinning hall is
50ft by 40ft with 12 fts clear head. The size of the kittchen
is 19ft by 25ft with 15ft clear head.
|
Estimated Cost Budget of Dinning
Hall
|
Names of Particular |
Nepalise Rupees (NRS) { NRS 70 = $ 1 U.S.) |
U.S Dollar ($) { $1 = NRS 70) |
Foundation & Plinth: |
191,752.00 |
2,739.31 |
Ground floor: |
515,780.00 |
7,368.29 |
Total |
707,532.00 |
10,107.60 |
5% Electric Cost: |
35,376.60 |
505.38 |
%Sanitary Cost: |
35,376.60 |
505.38 |
Subtotal |
778,285.20 |
11,118.36 |
5% Contingency |
38,914.26 |
555.91 |
|
|
|
Estimated Cost Budget of Kitchen
|
Names of Particular |
Nepalise Rupees (NRS) { NRS 70 = $ 1 U.S.) |
U.S Dollar ($) { $1 = NRS 70) |
Foundation & Plinth: |
87,269.00 |
1,246.70 |
Ground floor: |
246,669.00 |
3,523.84 |
Total |
333,938.00 |
4,770.54 |
5% Electric Cost: |
16,696.90 |
238.53 |
%Sanitary Cost: |
16,696.90 |
238.53 |
Subtotal |
367,331.80 |
5,247.60 |
5% Contingency |
18,366.59 |
262.38 |
Grand
Total |
385,698.39 |
5509.99 |
Multipurpose
Auditorium Hall |
|
The
auditorium Hall is designed to serve a community centre.
All indoor public presentations and gathering will take
place in the hall. While the school building works will
be undergoing, workers will use the hall.
The hall size is 40ft width by 60ft
length with 16ft clear head. The hight of the hall will
be same as the other two-story blocks. |
Estimated Cost Budget of the
Auditorium Hall
|
Name Of Particulars |
Nepalise Rupees (NRS) { NRS 70 = $ 1 U.S.) |
U.S Dollar ($) { $1 = NRS 70) |
Foundation & Plinth: |
298,491.00 |
4,264.16 |
Ground floor: |
580,887.00 |
8,298.39 |
Total |
879,378.00 |
12,562.54 |
5% Electric Cost: |
43,968.90 |
628.13 |
%Sanitary Cost: |
43,968.90 |
628.13 |
Subtotal |
967,378.00 |
13,819.69 |
5% Contingency |
48,365.79 |
690.94 |
Grand
Total |
1,015,681.59 |
14,509.74 |
Note: Let us know
if you like to receive more detailed information regarding
each part of building work and their cost. The budgets
and designs may differ slightly from actual cost and shapes.
It is because the engineers don't have any experience
working in a place like Limi and similar climate and geographical
conditions. Also, the budgets doesn't include transportation
of the building materials, which will be costly and difficult
to transfer because of the remoteness and inaccesssibility
of Limi.
|
|