Building
Graphics and Estimated Budgets of Each Block
The
following blocks will only be built after the completion
of the Phase One Part
of the school project. The Information about
the block designs and the estimated cost budgets are prepared
by two experts in engineering in Nepal.
At the Completion of the Phase One School Building Project,
Limi School start to hold classes.
The Libarary,
Science Laboratory, and Staff Office
The
Science Laboratory and the Staff Office are on the ground
floor. The Spacious library on the first floor is designed
to have tables and chairs for studying in it.
The size of the Science Laboratory and
the Staff Office are 30ft by 40ft with 8ft clear head. The
library size is 30ft by 80ft with 8 ft clear head.
Estimated
Cost Budget of The Science Laboratory, Library and Staff
Office Block
Names
of Particular
Nepalise
Rupees (NRS) { NRS 70 = $ 1 U.S.)
U.S
Dollar ($) { $1 = NRS 70)
Foundation & Plinth:
258,943.00
3,694.90
Ground floor:
864,530.00
12,350.43
First floor:
803,214.00
11,474.49
Total:
1,926,687.00
27,524.10
5% Electric cost:
96,334.35
1,376.21
5% sanitary cost:
96,334.35
1,376.21
Sub
Total:
2,119,355.70
30,276.51
5% Contingency:
105,967.79
1,513.83
Grand
Total:
2,225,323.49
31,790.34
Grant
Toal In words:
Twenty
Two Lakhs Twenty Five Thousand Three Hundred Twenty Three
and Fourty Nine Piasa.
Thirty
One Thousand Seven Hundred Ninety and 34 cent.
The Staff Residents
Two staff residents blocks share the same internal designs
and sizes. The staff block 'A' has an extra balcony and
a common corridor and is designed for the senoir teachers.
Each block has accommodation up to eight staff members.
The sizes of the rooms are 11ft by 12ft and the kitchens
are 5ft by 8ft with 8ft clear head.
Estimated Cost
Budget of the Staff Resident "B"
Names
of Particular
Nepalise
Rupees (NRS) { NRS 70 = $ 1 U.S.)
U.S
Dollar ($) { $1 = NRS 70)
Foundation & Plinth:
168,743.00
2,410.61
Ground floor:
739,775.00
10,568.21
First floor:
576,140.00
8,230.57
Total:
1,484,658.00
21,209.40
5% Electric cost:
74,232.90
1,060.47
5% sanitary cost:
74,232.90
1,060.47
Sub
Total:
1,633,123.80
23,330.34
5% Contingency:
81,656.19
1,165.17
Grand
Total:
1,714,779.99
24,496.86
Grant
Toal In words:
Seventeen
Lakhas Four Thousands Seven Hundred Seventy Nine and Ninety
Nine Piasa only
Twenty Four Thousands Four Hundred Ninety Six and Eight
Six cent only
Estimated Cost
Budget of the Staff Resident "A"
Names
of Particular
Nepalise
Rupees (NRS) { NRS 70 = $ 1 U.S.)
U.S
Dollar ($) { $1 = NRS 70)
Foundation & Plinth:
233,278.00
3,332.54
Ground floor:
626,181.00
8,945.44
First floor:
752,088.00
10,744.11
Total:
1,611,547.00
23,022.10
5% Electric cost:
80,577.35
1,151.11
5% sanitary cost:
80,577.35
1,1,151.11
Sub
Total:
1,772,701.70
25,324.31
5% Contingency:
88,635.09
1,266.22
Grand
Total:
1,861,336.79
26,590.53
Grant
Toal In words:
Eighteen
Lakhs Sixty One Thousands Three Hundred Thirty Six and Seventy
Nine Piasa only.
Twenty Six Thousands Five Hundred Ninety and Fifty Three
Cent Only.
The
Health-Care Center
Health-Care Centre and Administrative
Office have similar design and size. Both are single-story
houses.
There is a room for medecines storage,
a room for a doctor, and a kitchen. Some beds will be there
to keep patiences in the clinic if it is necessary.
The three villages of Limi doesn't have a real clinic to
go. Therefore, the Health-Care Centre is very important
to have at the school and will also serve the villagers.
The size of the patiences room and lobby
is 26fts by 23 ft and the size of the doctor's room and
the medicine store room are 8ft by 8fts and and the size
of the kitchen is 8ft by 5 ft with 8ft clear head.
Estimated
Cost Budget of the Health Care Centre
Names
of Particular
Nepalise
Rupees (NRS) { NRS 70 = $ 1 U.S.)
U.S
Dollar ($) { $1 = NRS 70)
Foundation & Plinth:
109,718.0
1,567.40
Ground floor:
299,608.00
4,280.11
Total:
409,326.00
5,847.51
5% Electric cost:
20,466.30
292.38
5% sanitary cost:
20,466.30
20,466.30
Sub
Total:
450,258.60
6,432.27
5% Contingency:
22,512.93
321.61
Grand
Total:
472,771.53
6,753.88
Grant
Toal In words:
Four
Lakhas Two Thousands Seven Hundred Seventy One and Fifty
Three Piasa only.
Six Thousand Seven Hundred Fifty Three and Eight Eight
Cent only.
The Administrative
Office
The
administrative Office has an office for the school
principle. There is a smaller room for storying students'
and school files and a kitchen to prepare teas and lunches.
The Receptoin room is the the biggest room where visitors
wait and use as indoor meeting place.
The size of the Recenption is 23 ft
by 16ft. The Principle Office is 8ft by 11ft . The file
Storage is 8ft by 8ft and the kitchen is 8ft by 5 ft with
8ft clear head.
Estimated
Cost Budget of the Adnimistrative Office
Names
of Particular
Nepalise
Rupees (NRS) { NRS 70 = $ 1 U.S.)
U.S
Dollar ($) { $1 = NRS 70)
Foundation & Plinth:
109,718.0
1,567.40
Ground floor:
299,608.00
4,280.11
Total:
409,326.00
5,847.51
5% Electric cost:
20,466.30
292.38
5% sanitary cost:
20,466.30
20,466.30
Sub
Total:
450,258.60
6,432.27
5% Contingency:
22,512.93
321.61
Grand
Total:
472,771.53
6,753.88
Grant
Toal In words:
Four
Lakhas Two Thousands Seven Hundred Seventy One and Fifty
Three Piasa only.
Six Thousand Seven Hundred Fifty Three and Eight Eight
Cent only.
The
Guest House
Guest rooms are for school supporters,
lecturers, and visitors.
All guest rooms have a great view of
the surrounding environment and are designed to be spacious
and private. It is expected the most guests would
Estimated Cost
Budget of the Guest House
Names
of Particular
Nepalise
Rupees (NRS) { NRS 70 = $ 1 U.S.)
U.S
Dollar ($) { $1 = NRS 70)
Foundation & Plinth:
168,743.00
2,410.61
Ground floor:
739,775.00
10,568.21
First floor:
576,140.00
8,230.57
Total:
1,484,658.00
21,209.40
5% Electric cost:
74,232.90
1,060.47
5% sanitary cost:
74,232.90
1,060.47
Sub
Total:
1,633,123.80
23,330.34
5% Contingency:
81,656.19
1,165.17
Grand
Total:
1,714,779.99
24,496.86
Grant
Toal In words:
Seventeen
Lakhas Four Thousands Seven Hundred Seventy Nine and Ninety
Nine Piasa only
Twenty Four Thousands Four Hundred Ninety Six and Eight
Six cent only
Common
Toilets
In total, there are six common toilets.
Two smallers toilets are for the staff residents and the
guest house. There are two common toilets for the hostals
blocks and two common toilets for the academic blocks.
All toilets are separate for male and
female and are designed to use as local system, which means
no running water and all waste will use as fertilizer for
growing barley and vegetable.
Estimated
Cost Budget of the Guest House
Names
of Particular
Nepalise
Rupees (NRS) { NRS 70 = $ 1 U.S.)
U.S
Dollar ($) { $1 = NRS 70)
Foundation & Plinth:
53,517.00
764.53
Ground floor:
211,573.00
3022.48
Total:
265,090.00
3,787.00
5% Electric cost:
13,254.50
189.35
5% sanitary cost:
13,254.50
189.35
Sub
Total:
291,599.00
4,165.70
5% Contingency:
14,579.95
208.29
Grand
Total:
306,178.95
4,373.99
Grant
Toal In words:
Three
Lakhas Six Thousands One Hundred Seventy Eight and Ninety
Five Paisa Only.